PYR – Basketball Lobby Refresh

Scope of work includes painting and graphics in the Pyramid basketball lobby, in addition to installation of wall guards.

  • Total Project Cost:  $93,000
  • Construction Start Date:  July 27, 2026
  • Construction Completion Date: August 23, 2026
  • Project Delivery Method: Construction Manager at Risk, Exbon Development
  • DCS Design Team: Marlen Cruz
  • DCS Construction Manager: Matthew Ramirez