MSX Accessible Parking Masterplan

Scope of work includes adding accessible stalls to (9) parking lots across campus. The construction will occur in 2 phases. Phase 1 will occur in parking lots E3, E5, E7, E9, E10, and the Pyramid Parking Structure. Phase 2 will occur is parking lots E2, R2, and G10.

  • Total Project Cost:  $779,000
  • Phase 1 - Construction Start Date:  July 20 2026
  • Phase 1 - Construction Completion Date: August 21, 2026
  • Phase 2 - Construction Start Date:  December 28, 2026
  • Phase 2 - Construction Completion Date: January 20, 2027
  • Project Delivery Method: Construction Manager at Risk, Exbon Development
  • Architect: 19Six
  • DCS Construction Manager: Matthew Ramirez