Blair Field Seating Repairs Phase 2

Scope of work includes the repair of seating and installation of handrails and guardrails.

  • Total Project Cost:  $985,000
  • Construction Start Date:  October 1, 2026
  • Construction Completion Date: November 30, 2026
  • Project Delivery Method: Exbon Development
  • Structural Engineer: MHP
  • DCS Construction Manager: Taylor Gibbons