BH Level 3 Restrooms

Scope of work includes the renovation of the Brotman Hall Level 3 Men’s and Women’s Restrooms including, ADA Upgrades, replacement of the plumbing and lighting fixtures, new toilet partitions, re-finish of wall & floor tiles, and painting of walls and ceilings.

  • Total Project Cost:  $536,000
  • Construction Start Date:  June 29, 2026
  • Construction Completion Date: September 11, 2026
  • Project Delivery Method: Construction Manager at Risk, Exbon Development
  • Architect: MMA
  • DCS Construction Manager: Taylor Gibbons