BH Level 3 Restrooms
Scope of work includes the renovation of the Brotman Hall Level 3 Men’s and Women’s Restrooms including, ADA Upgrades, replacement of the plumbing and lighting fixtures, new toilet partitions, re-finish of wall & floor tiles, and painting of walls and ceilings.
- Total Project Cost: $536,000
- Construction Start Date: June 29, 2026
- Construction Completion Date: September 11, 2026
- Project Delivery Method: Construction Manager at Risk, Exbon Development
- Architect: MMA
- DCS Construction Manager: Taylor Gibbons